Here is the weekly road construction report for Hamilton County:

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone is 45 MPH.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  On weekdays during this report period between the hours of 9 a.m.-3 p.m., the contractor will have a temporary right lane closure on eastbound MLK Blvd. between the U.S. 27 North exit ramp and Carter St. and on westbound MLK Blvd. between Chestnut St. and the U.S. 27 North entrance ramp to work on new signals.  Ramp traffic will not be affected.  This work is weather permitting.  As the project progresses, there may be short term temporary lane closures for the safety of the traveling public on city streets within the project area.  Flaggers will assist with these closures and they will be properly signed in accordance with the Federal Highway Administration’s Manual on Uniform Traffic Control Devices. During Phase 1 of the U.S. 27 project, the contractor will be working on the northbound side of U.S. 27 on the bridges.  Work will consist of demolishing and reconstructing the outside sections of the bridges along U.S. 27 North.  Also on U.S. 27 South, they will be constructing a large retaining wall between the Olgiati Bridge and 6th Street.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  The contractor will implement a new traffic pattern at the intersection of Apison Pike and Ooltewah-Ringgold Road on Thursday beginning at 8 p.m., weather permitting.  Flaggers will assist with traffic control as needed.  During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m.  Flaggers will assist with traffic control as needed.  Estimated project completion date is May. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  Traffic has been switched onto the newly-constructed section from the west end of the project to the Hurricane Creek Rd./East Brainerd Rd. intersection, allowing the contractor to work on the other side of the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Original completion date is June. Estimated project completion date is December. [Jones Brothers Contractors, LLC /Pruett/CNN383] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153:  Work on this project continues. The outside lanes in both directions on the bridge on Hixson Pike over SR-153 are now closed.  This lane closure will be in place until late November.  During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge.  If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m.-3 pm.  Flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941] 

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs normally on Wednesday and Thursday nights during the week with the 3rd Tuesday of the month.  Work hours are between 8 p.m.-6 a.m. Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June.  [Diamond Specialized, Inc./Micka/CNQ174]




McKamey Animal Center To Hold 12-Hour Adoption Event On Friday

Home for the Holidays or Bust! That is the mantra of the staff and volunteers of local animal shelter McKamey Animal Center in Chattanooga. Volunteers and staff members are gearing up to help as many animals as possible find a home for the holidays. Shelter staff and volunteers will be staying for a "Holiday All-Nighter" at the shelter on  Friday, from noon until midnight ... (click for more)

Local Organizations Partner To Honor Veterans At Chattanooga National Cemetery

On Saturday, more than a dozen of the area volunteer organizations (including the Civil Air Patrol, Young Marines, Navy Sea Cadets, Girl Scouts, Boy Scouts, Cub Scouts, Brownies, Patriot Riders, Veterans of Foreign Wars, Daughters of the American Revolution, Sons of the American Revolution, employees from U.S. Xpress and Covenant Transport and more) will be participating in the ... (click for more)

Home In Alton Park Damaged By Fire Friday Morning

No injuries were reported in connection with a house fire in Alton Park Friday morning. The Chattanooga Fire Department received the alarm around  8:30 a.m.  and responded to 4020 Highland Ave. with five fire companies. When the first firefighters arrived on the scene, one of the residents of the house was concerned this his wife might still be inside. The firefighters ... (click for more)

Cliftina Jones Charged In Death Of Orange Grove Center Client, Whose Body Was Found In Van

A Chattanooga woman has been charged in the death of an Orange Grove Center client whose body was found April 18 at an Orange Grove residence. Cliftina K. Jones, 60, was indicted by a Hamilton County Grand Jury on a charge of criminally negligent homicide. Police said at the time there was no sign of trauma on the body of 60-year-old Carrie Lee Parkey. S taff at ... (click for more)

Technology: The Virtual Drug

The truth is you're probably reading this on a mobile device or your computer. As a matter of fact, I’m typing this down on a MacBook Pro. The point is technology is everywhere. It engulfs like a tsunami engulfs a village, only a few ever escape. In fact, it took me two hours to start this paper because I was so hypnotized by phone, checking my Instagram and seeing what the next ... (click for more)

Roy Exum: The Lesbian’s Daddy

I’ve always held the belief that things work out for the best. Oh, I’ve been in some tights where I couldn’t see the forest for the trees but, in the up-and-down life I have lived, I’ve found that God doesn’t make mistakes. If I’ll just hold on long enough, no matter how bad the circumstances, something good will happen. It always does. One of the best examples I have seen lately ... (click for more)