Weekly Road Construction Report

Thursday, August 9, 2018

Here is the weekly road construction report for Hamilton County: 

I-75 North Exit 1 interchange reconfiguration project at mile marker 1:   Work on this project continues. There is now only one exit ramp that allows drivers to turn both east and west on Ringgold Road at a signalized intersection. Traffic has been shifted onto the newly constructed portion of Camp Jordan Parkway, and the intersection (I-75 NB off-ramp and SR-8/Camp Jordan Parkway) is now controlled by a traffic signal. Estimated project completion date is August. [C.W. Matthews Contracting/City Of East Ridge/LCLPRGM]  

US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:   Work on this project continues with numerous activities occurring in the median of US-27. Motorists should be alert for construction vehicles entering and leaving the left traffic lane in both the northbound and southbound directions. The 12th Street tie-in ramp to US-27 South has been temporarily closed. This closure will be in place through September. Detours are posted. Motorists should exercise caution when traveling through the construction zone and pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting, the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 p.m.-6 a.m. At least one lane will remain open in each direction on US-27. THP will assist with traffic control on the project as necessary. RESTRICTIONS: Northbound US-27 off-ramp Exit 1C to 4th Street is restricted to a maximum width of 11 Feet. Estimated project completion date is January 2020. [Dement Construction Company, LLC/Micka/CNP230]  

US-127 (SR-8) slope repair of Signal Mountain Blvd. at log mile 15.9:   During this report period, the contractor will have one lane closed while performing slope stabilization operations. Temporary traffic signals are in place on either end of the project to control traffic. Additionally the speed limit has been lowered to 20 MPH in the construction zone. Additional flaggers will assist with traffic control as needed. RESTRICTIONS: Reduced to one 10-foot 5-inch lane Estimated project completion date is September. [GSI/Maintenance/MAINT]  

SR-153 resurfacing from I-75 (LM 0.00) to Shallowford Road (LM 2.60), including bridge deck repair:   Night time lane closures from 8 p.m.-6 a.m. Sunday-Thursday on SR-153. Estimated project completion date is November. [Wright Brothers Construction Company, Inc./Micka/CNS251]  

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:   During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m. This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Bel-Air Road. Flaggers will assist with traffic control as needed.  Estimated project completion date is August. [Jones Bros. Contractors, LLC/Pruett/CNN383] 

US-11/64 SR-2 (Brainerd Road/Lee Highway) resurfacing from east of Moore Road (LM 13.85) to east of Airport Road (LM 15.84):  The contractor has begun lowering manholes and catch basins. This will take place Monday through Friday between 9 a.m.- 3 p.m. This work may affect either direction of US-11/64 (Brainerd Road/Lee Highway) between Moore Road and Airport Road. The contractor will begin milling and paving on Aug. 26, after which the contractor will have intermittent lane closures for resurfacing operations Sunday through Thursday from 8 p.m.-6 a.m. Flaggers will assist with traffic control as needed. Estimated project completion date is November. [Wright Brothers Construction Co., Inc./Pruett/CNS228] 




Hospice Of Chattanooga Hosts Memorial Service For Those Grieving Loss Of Loved Ones

Hospice of Chattanooga is hosting a memorial service on  Sunday, Aug. 26, for anyone who has gone through the death of a loved one. This service is for all in the community, who are experiencing grief, regardless of whether their loved one died under hospice's care or not.  The service will begin at  2 p.m  at First Christian ... (click for more)

Williams Street To Be Closed Wednesday And Thursday For Water Meter Installations

Williams Street, between 1400 and 1410 Williams Street,  will be closed on  Wednesday  and  Thursday, from 9 a.m. until 3 p.m.  for water meter installations. L ocal traffic still able to access businesses and residences from East Main Street. View CDOT's map of event and road closures   for full details of projects underway ... (click for more)

NAACP Wants Answers On Snafu That Caused 43 Ballots Not To Be Counted In Recent Hamilton County Election

Officials of the NAACP said they have "grave concerns" about an election snafu in Hamilton County that left the ballots of 43 voters uncounted in the Aug. 2 election. The group said there has been little information given on the complex problem involving an earlier shift in voter lines. They have written a letter to Mark Goins, state election coordinator, and Kerry Steelman, ... (click for more)

Hearing Delay On Suit Brought By State Democrats To Keep Robin Smith Off Ballot

A hearing has been delayed on a lawsuit brought by the Tennessee Democratic Party seeking to keep Republican Robin Smith off the ballot in House District 26. Ms. Smith was the only candidate after longtime Rep. Gerald McCormick abruptly announced he was leaving his post to move to Nashville. Chancellor Jeff Atherton on Monday afternoon said he could not take the case until ... (click for more)

Make One Of The Proposed Surplus City Buildings Into A Local History Museum - And Response

The city of Chattanooga currently has no history center or museum. That is because several years ago it was conveyed to the public, in the blinking of an eye, that $9 million that had been raised mysteriously vanished for reasons unexplainable to this date. In the meantime, valuable artifacts and collections are sitting in cellars, basements and storage facilities instead of being ... (click for more)

Roy Exum: No Cell Phones Allowed

There was a time, not so long ago, when school-aged children would learn lessons from a prescribed text, such as a textbook. Today texting is far, far different and, as any of our teachers will tell us, cell phones have become the scourge of education. In almost every classroom, kids will silently text in the shadow of the desk in front of them rather than focus on the lesson. Yet ... (click for more)